Overview

Basics

Basics
Near Meeks Bay, at Meeks Creek Bridge No. 25-0019. Replace Meeks Creek Bridge, restore creek to address bridge scour and fish passage barriers, add wildlife terrestrial crossing improvement under bridge, and add bicycle and pedestrian improvements. EA: 4J090

Planning/Design
2023
2026
2030
$25,070,000

Joan Davis (D3.FTIP@dot.ca.gov)
09/21/2023
02/14/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes
Postmiles 24.4 - 25.3

Organizations

Organizations
California Department of Transportation (Caltrans) Joan Davis - California Department of Transportation (Caltrans)

EIP Details

EIP Basics

03.02.02.0103 - Meeks Creek Bridge - SHOPP Project

This project is on the EIP 5-year list.

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2030 2029 2028 2027 2026 2025 2024 2023
SHOPP Funds (Caltrans) $25,070,000
Preliminary Engineering $4,990,000 $0 $0 $0 $0 $0 $2,990,000 $0 $2,000,000
Right of Way (aka Land Acquisition) $1,890,000 $0 $0 $0 $0 $1,550,000 $340,000 $0 $0
Construction $18,190,000 $0 $0 $0 $0 $18,190,000 $0 $0 $0
Grand Total $25,070,000 $0 $0 $0 $0 $19,740,000 $3,330,000 $0 $2,000,000

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$25,070,000
$25,070,000
$0

Total
SHOPP Funds (Caltrans) $25,070,000 $25,070,000 $0
Grand Total $25,070,000 $25,070,000 $0

Reported Expenditures

Reported Expenditures
Total 2023
SHOPP Funds $527,182 $527,182
Grand Total $527,182 $527,182

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

  • Construct a fish management structure in the creek. The fish management structure should consist of a weir or similar in-channel structure that can be adjusted to block or allow the movement of fish.
  • Construct a bicycle/pedestrian single span bridge along SR 89 vehicular bridge over Meeks Creek. The bridge shall be constructed for vehicular loading with traveled way width of 12’. The bridge shall be constructed in alignment with the draft SR 89 Trail Feasibility Study recommendation. Stripe centerline with 4” traffic stripe and pavement markings.
  • Construct wildlife terrestrial improvements under the bridges.

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

03.02.02.0103 - Meeks Creek Bridge - SHOPP Project is associated with following groups of projects.

External Links

No external links entered.

Notes

Notes
02/14/2024 11:54 AM Beth Vollmer Changing the action priority from Build and Enhance Transit Systems to Build and Enhance Trail Systems. Old EIP #03.02.02.0103
01/12/2024 2:21 PM Beth Vollmer Previous EIP number 03.02.01.0065