Overview

Basics

Basics
The project improved treatment of stormwater runoff in Kahle Basin by increasing basin treatment capacity and effectiveness and improving conveyance capacity along Kahle Drive. The multi-benefit project also enhanced existing recreational access in Rabe Meadow through the next phase Kahle Complete Street. The project was registered in the LT Info Stormwater Tools in 2018 with a potential of 51 lake clarity credits. See https://stormwater.laketahoeinfo.org/BMPRegistration/Detail/163 for more information on the registration.

Completed
2015
2018
2018
$1,356,750

Meghan Kelly (mkelly@ntcd.org)
03/14/2017
01/19/2021
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

Lake Clarity Details

Lake Clarity Basics

Lake Clarity Basics

Urban Stormwater Questionnaire

The Urban Stormwater Questionnaire is not relevant because this project is not seeking voter-approved bond funding through the State of California consistent with the Stormwater Resource Plan (SRP).

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Roads Decommissioned or Retrofitted None miles
Miles of Trails Developed or Improved None miles

Reported Performance Measures

Reported Performance Measures
Miles of Roads Decommissioned or Retrofitted
2018 Total Units
Property Ownership Road Type Treatment Type
Douglas County Paved Retrofitted 0.43 0.43 miles
Nevada Department of Transportation Paved Retrofitted 0.4 0.4 miles
Total 0.83 0.83 miles

Funding

Expected Funding

Expected Funding
$1,356,750
$1,356,750
$0

Total
Nevada Department of Transportation (NDOT) $250,000 $250,000 $0
Private Property Owners (Private) $5,000 $5,000 $0
SEZ Mitigation Funds (TRPA) $118,000 $118,000 $0
Southern Nevada Public Land Management Act (USEPA) $10,000 $10,000 $0
Southern Nevada Public Land Management Act (USFS - LTBMU) $611,500 $611,500 $0
Tahoe Bonds Act (NDSL) $194,250 $194,250 $0
U.S. Natural Resource Conservation Service (NRCS) $26,000 $26,000 $0
WQ Mitigation Funds (TRPA) $142,000 $142,000 $0
Grand Total $1,356,750 $1,356,750 $0

Reported Expenditures

Reported Expenditures
Total 2018 2017 2016 2015
Nevada Department of Transportation $235,000 $235,000 $0 $0 $0
SEZ Mitigation Funds $118,000 $106,250 $11,750 $0 $0
Southern Nevada Public Land Management Act $10,000 $0 $0 $0 $10,000
Southern Nevada Public Land Management Act $611,500 $608,066 $3,434 $0 $0
Tahoe Bonds Act $194,750 $194,750 $0 $0 $0
U.S. Natural Resource Conservation Service $26,000 $0 $22,000 $4,000 $0
WQ Mitigation Funds $142,000 $142,000 $0 $0 $0
Grand Total $1,337,250 $1,286,066 $37,184 $4,000 $10,000

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

No Local and Regional Plans set for this project.

Related Projects

Related Projects

01.01.01.0150 - Kahle Water Quality Basin Implementation is associated with following groups of projects.

External Links

Notes

Notes
01/13/2020 3:35 PM Beth Vollmer Retrofits are taking place as part of project 03.01.02.0143 - Kahle Complete Street Project. Make sure accomplishments are not reported as part of both projects.
01/02/2020 12:45 PM Meghan Kelly Reported 0.83 miles of road retrofit but retrofit will not be complete until Kahle Complete Street is implemented.
12/20/2018 10:51 AM Beth Vollmer Performance Measures will be reported on in phase two of this project